Muhammad AbdullatifApr 132 minInnovation Unfolds: The Final ChapterThe team communicated with the manufacturer, Laser Welding Solutions, throughout the work period, as there had been ongoing manufacturing...
Muhammad AbdullatifMar 232 minJourney to Prototype PerfectionDuring this work period, Team 16 has completed and received final approval from the project sponsor, HMH, for our manifold FEAs. 3D...
Muhammad AbdullatifFeb 181 minCrafting Prototype PathwayDuring the past two weeks, the team continued to work diligently on creating accurate FEA results to get final approval from our...
Muhammad AbdullatifFeb 42 minBack & BetterThroughout the break, Team 16 maintained frequent meetings with HMH. The sponsor requested that the CAD be changed to allow for a higher...
Muhammad AbdullatifNov 26, 20232 minThe Final TouchesOver the past two weeks, team 16 has completed Milestone 3. As of November 18, the final three tasks had been completed. Comprehensive...
Muhammad AbdullatifNov 11, 20232 minProgress and PlansThe full CAD model has been completed and is shown in Figure 1. The device has been split into 3 separate parts by maneuvering around the...
Muhammad AbdullatifSep 30, 20232 minChallenges of the ManifoldVerifying if our design will be easily manufactured is the critical challenge. The hydraulic manifold's various complex internal...
haijaayatSep 9, 20232 minSubsea Hydraulic ManifoldLate deliverables on engineering projects can create a strained relationship between the company and the customer. Every day a product is...